Just got back from a flight over Mcity. M1 should have the last bit of roof poured this week and it looks like M2 is probably a month to six weeks away from that.
 

Tim MacDonald

Senior Member
Member Bio
Joined
Dec 8, 2011
Messages
2,197
Reaction score
7,194
Location
Mississauga
Sep 3rd
DJI_0152.JPG
DJI_0156.JPG
DJI_0158.JPG
DJI_0155.JPG
DJI_0148.JPG
 

Tim MacDonald

Senior Member
Member Bio
Joined
Dec 8, 2011
Messages
2,197
Reaction score
7,194
Location
Mississauga
M1 & M2 Officially Topped Off on 14 Sep 2022 >
OOOOOOOOOOOKKKKKKKKKKKKKK
That video seemed rather pointless. I was hoping for a crane or drone POV video of the last bit of cement being poured.
 

Tim MacDonald

Senior Member
Member Bio
Joined
Dec 8, 2011
Messages
2,197
Reaction score
7,194
Location
Mississauga

Tim MacDonald

Senior Member
Member Bio
Joined
Dec 8, 2011
Messages
2,197
Reaction score
7,194
Location
Mississauga
Well, I don't know where that fog and low cloud came from this morning but I was there so I photographed it anyway.

It looks like M1 just needs one last concrete pour:
DJI_0476.JPG


Literally a few metres lower and the viz was better:
DJI_0477.JPG


Tower 2 still requires a lot of work:
DJI_0478.JPG
 

seankga

New Member
Member Bio
Joined
Sep 9, 2022
Messages
3
Reaction score
0
"The M1 and M2 towers are nearing superstructure completion this fall, standing over 60-storeys complete with above and below-grade parking, interior and exterior amenity areas, as well as commercial spaces on the ground floor." - EllisDon

View attachment 422410

View attachment 422411

View attachment 422412
Hi there! I work with a team that manages M City's Instagram account. Would you be open to us re-posting these photos on the account? We would, of course, provide a photo credit in the caption.
 

drum118

Superstar
Member Bio
Joined
Apr 24, 2007
Messages
18,764
Reaction score
17,872
Location
Mississauga, where cars rule city growth
Sept 26
They put the shoring for the north end of M1 roof area not form about 2 weeks ago and it is know pour. The rest of the shoring has been removed.

Forming still on going for M2 roof for the centre section that will be pour first and then one end at a time like M1 from what I seen so far.

These are unedited photos and a few of the 200 I have shot this months that in my backlog of photos going back to July 20

Sept 11
133A2472.JPG
133A2474.JPG
133A2489.JPG


Sept 26 Top off
133A2763.JPG
 

Tim MacDonald

Senior Member
Member Bio
Joined
Dec 8, 2011
Messages
2,197
Reaction score
7,194
Location
Mississauga
It's pretty clean at the top of M1 - photo from September 25th. Haven't had a chance to go through all of them yet but thought I would drop this one to give @drum118 photos some context.
DJI_0082.JPG


Is there any way I can find out when the crane is being removed? I'd love to shoot that.
 