Toronto Lower Don Lands Redevelopment | ?m | ?s | Waterfront Toronto

Took a quick pic of 2 new concrete supports for the north end of the new cherry st alignment.

PXL_20210409_205016228_2.jpg
 
Looks like a new construction timeline video posted by Waterfront Toronto, rebaselined in February.
They seem to be expecting the Commissioners St. bridge west section on or about the 26th of this month (02:40) and the east section on or about June 7th (02:49)
Looks like they will be barged to the old foot of the Don Roadway in the shipping channel and transported up to the bridge location.
 
Last edited:
April 7
Now to back fill and build the new road while waiting for the new bridge that will be arriving in a few months. The the cutting of the new mouth of the Don after the road is open and the Old Cherry St Close.
51112841566_719f90d4af_b.jpg

51112597009_91b62e8b93_b.jpg

51112749013_a070e4de28_b.jpg

51112276462_9b91c75fbf_b.jpg
 
Looks like a new construction timeline video posted by Waterfront Toronto, rebaselined in February.
They seem to be expecting the Commissioners St. bridge west section on or about the 26th of this month (02:40) and the east section on or about June 7th (02:49)
Looks like they will be barged to the old foot of the Don Roadway in the shipping channel and transported up to the bridge location.
Thanks for posting this! It's nice to see half the new cherry street alignment will be open by the end of the year
 
View of the future site of Atlas Crane Peninsula and Promontory Park South engulfed by thick fog last night. The 300-ton Atlas Crane rises above the fog on the right and Lafarge Cement facility is shrouded on the left. Shot from my balcony in the Distillery District. Anybody know what will happen to the Lafarge facility ?

_1180225 (1).jpg
 
Last edited:
View of the future site of Atlas Crane Peninsula and Promontory Park South engulfed in thick fog last night. The 300-ton Atlas Crane rises above the fog on the right and Lafarge Cement facility is shrouded on the left. Shot from my balcony in the Distillery District.

View attachment 312673

Cue Sherlock Holmes entry...
 
Google's 3D map of Toronto updated recently. Although it's still woefully out of date, it really shows how big the project is.

UT1.png
UT2.png

From: https://goo.gl/maps/4Nmkm72XYc73PuV87


Based on it showing buildings being demoed at YSL means these were likely taken early summer of 2019. It's crazy how much has been done since then. It's also interesting to see all the new buildings that have been built since the map has last been updated.
Matched to this post: https://urbantoronto.ca/forum/threa...cresford-kohn-pedersen-fox.17678/post-1455944 would be June 2019.
UT3.png
 
Google's 3D map of Toronto updated recently. Although it's still woefully out of date, it really shows how big the project is.

View attachment 313179View attachment 313180
From: https://goo.gl/maps/4Nmkm72XYc73PuV87


Based on it showing buildings being demoed at YSL means these were likely taken early summer of 2019. It's crazy how much has been done since then. It's also interesting to see all the new buildings that have been built since the map has last been updated.
Matched to this post: https://urbantoronto.ca/forum/threa...cresford-kohn-pedersen-fox.17678/post-1455944 would be June 2019.
View attachment 313183
I think it might be earlier than 2019, I don't even see Aiken Park or Aquabella started yet?
 

Back
Top