This is the current construction schedule for 8 The Esplanade – L Tower – for May 7 – 11, 2012
Posted May 4, 2012
Note: The L Tower is scheduled to reach 40 floors this week.
Monday, May 7
A 190M slab concrete pour, level 39, starting 10:00 am,, which is not expected to extend beyond 7:00 pm.
Tuesday, May 8
A 99M (part 1) wall and column concrete pour, levels 39 – 40 starting 1:00 pm, which is not expected to extend beyond 7:00 pm.
The hoist will be raised three (3) floors, to stop at level 33.
Wednesday, May 9
Rebar (steel) delivery starting at 12:30 pm.
Please note that eastbound vehicular traffic may be interrupted during this delivery.
Pedestrian traffic will remain open.
Please click here for a photograph of a midday rebar (steel) delivery.
A 108M (part 2) wall and column concrete pour, levels 39 – 40, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.
Thursday, May 10
Rebar delivery starting at 7:00 am.
Rebar delivery starting at 12:30 pm.
Please note that eastbound vehicular traffic may be interrupted during this delivery.
Pedestrian traffic will remain open.
Please click here for a photograph of a midday rebar (steel) delivery.
Friday, May 11
A 190M slab concrete pour, level 39, starting 10:00 am, which is not expected to extend beyond 7:00 pm.
Rebar delivery starting at 12:30 pm.
Please note that eastbound vehicular traffic may be interrupted during this delivery.
Pedestrian traffic will remain open.
Please click here for a photograph of a midday rebar (steel) delivery.
* * *
NOTES:
Construction schedules are dependent on weather conditions.
A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.