Just got back from the planning committee meeting in Brampton....and the tunnel option(s) were, well, buried.
Council voted 10-0 (one councillor on vacation) on a) further study of either tunnel option and b) setting aside the $2.5MM that staff had requested to study those options further.
Council then voted on a motion put forward by Councillor Spovieri to direct staff to, for the first time, engage "experts" to present cost benefit analysis on 3 of the alternative routes. It was then moved that, rather than collectively, each of those be separate votes.
- Elevated through the park.....studying this received 8 yes votes and 2 nays....so it will be studied
- Steeles to Kennedy to Queen to GO.....studying this received 8 yes votes and 2 nays....so it will be studied
- Steeles to McLaughlin to Orangeville railway to GO...studying this received 4 yes votes and 6 nays....so will not be studied.
Long meeting (was the 8th agenda item)....and some predictable goings on...but that is the gist of it. Unless something strange happens, the route from Gateway to DT GO will
not be up Main (either surface or tunnelled).