Nov 6
Looks like that the southbound curb lane will be fully pave between Fairview and Burnhamthorpe as they were working on an small section of the intersection at Central Parkway. Some manholes in the road are been worked on.
Paving taking place at a number of locations as well preparing southbound lanes to have curb pour along with the road to get ahead of the winter weather and to have 2 lanes open over the winter months.
The guideway base at Englewood has been pour.
Nov 5
Had a looked at the 401 area with tracks being installed in the guideway north of World Dr. From World Dr to the 401 off ramp has rail laying in the guideway with tracks in place with north being form and south been pour halfway point to the 401. A small section of the northbound track is pour in place midway Grading taking place from the 401 ramp to the overpass. Various sections of the overpass seeing concrete repairs taking place.
Small section of the guideway still needs to see the base pour from the 401 east off ramp to Britannia as well the curb. A second base about 4 inches has been pour for the northbound lane and no idea why or if the southbound will see the same thing. Near Britannia, the 4 curbs in the guideway has been pour for them.
The Britannia stop platform real close to the intersection compared to the ones already built. Waiting forming and having concrete pour for it.
Nov 1
The OMSF is about the same as I last saw it a few months ago. Poles have the bracket on them, but no OS. Sound barrier up along the northside, but stop short near Kennedy where the fence will jog about 50' to the north in drainage ditch. Crew was core drilling and pouring the footing for the fence post that will be anchor to the post footing at a later date.
Nothing on the 407 area other that it 100% pour for the guideway with track in place.
Topflight has seen foundation installed for the OS support along the southside with the road being prepared for the curb.
I counted no less than 40 workers on Topflight intersection and the most I have seen at any location. I may miss a few as a number where coming and going from the intersection. Would say 25% were working on the track work for the in/out bound track to the south. The other 75% were building forms for the inbound track as well a small section out bound that cross the northbound traffic lanes. Off hand, the inbound track could see the base by the end of the week. Work will move to the outbound next that will be follow by the tracks for the north end.
The southbound/ and the northbound track across the intersection will happen after the north tracks are done. The switches for both through track laying in the guideway to be built in December. Lots of splicing for both the northbound and southbound tracks
Once all the track base is in place, the road base will be pour follow by the top coat.
If they plan to shift the northbound lanes to the new area, there is no roadwork in place for the north end to the 407 overpass unless they plan on having having only one lane going north until next year when work can take place on the new road. This will allow the intersection to be open about year end and digging the guideway from the intersection to the section to the south.
Photos for Nov 5 will follow some time this week as too much on my plate at this time with a lot of photos for Nov 1 up on my site. Will break Nov 1 shots down into 2 posting