Since I still have a few hundred more photos to upload and tag, it allow me to get out and do some more shooting. Decided to have a look at the north end of the line and not much has change since Sept 10.
Monday may see the opening for left turns at the eastbound 401 on ramp as its paved with paving equipment still there. Don't know if anymore paving has to take place.
Wintergarden Intersection now close with the bottom of the guideway pour and could open by month end.
A few more sidewalk light post have been installed next to the road light/hydro poles that are short in height.
The base of Eglinton platform pour and working on the top forming. Britannia platform top is ready for pouring.
The north end of Matheson Platform for the northbound track is now pour in place with the track at the platform being wrap to be pour in place. Nothing so far done for the southbound track.
The areas south of Derry thar were being rebuilt is now done. What got me was the huge pad in mid block like it was done on Crosstown Line as I don't see a need for it and wasn't there before.
The last section to OMSF by the 407 terminal is pour with a small section of top coat to be pour.
Another section of Topflight has been pour that will allow better access to the motel and step closure to completing the road.
All the ties that were stockpile are now layout in the guideway with track being place on it. The grove that was on top of the ties is being used to anchor brackets that will be holding the rail in place. Still see nothing for switches yet with rail being place with groove support from 10-59 feet as per the markings on them. The crossing Tees are in place and small along the lines of TTC style. Still a lot of rail to be install as well splice. The straight track between the curves are the normal style of ties and rail
Looks like Nov/Dec before the work is done subject to switches.
A few shots unedited and hoping to have the rest on line by Tuesday