From the supporting materials for the last WT Investment and RE Committee:
Previous Period:
George Brown College will set up meeting with Redpath to address Redpath’s concerns with The Arbour. Risk Assessment for the Arbour site accepted by Ministry of Environment. Next Step: Draft Certificate of Property Use.
Next Steps:
Settlement reached between Redpath and George Brown in January 2021. Minutes of settlement executed and TLAB appeal withdrawn. Certificate of Property Use issued by Ministry of Environment. Record of Site Condition expected in March 2021.
Status:
Targeted construction start in April is pending outstanding comments from 2nd Site Plan Application submitted in September 2020.
From the March WT Investment and Real Estate Committee Meeting book:
Settlement reached between Redpath and George Brown in January 2021. Minutes of settlement executed and TLAB appeal withdrawn. Certificate of Property Use issued by Ministry of Environment. Record of Site Condition expected in March 2021
Targeted construction start in April is pending outstanding comments from 2ndSite Plan Application submitted in September 2020