It's the way how the project is delivered. If tunnelling and station excavation occurred at the same time like every other project in the work including the Sheppard subway and TYSSE, it could been a 2015 start and we are in the 8th year. Instead they came up with this stupid delivery method to push the spending to 1, 2 or even 3 election terms ahead and not balance the books today. Crosstown West and Scarborough subway extension is using this same tunnel first, dig later delivery. They won't even dig the stations till 2025/26 and if the screw up, they won't even open till 2032/33. If they would spend the money this election term and dig the stations starting in 2021 along with tunneling, we could have seen a possible opening targets in 2027. They are also cheap and wanted to order the minimum required TBM. If they ordered two pairs for the Crosstown west, they could have done the tunneling with an exit shaft at Kipling from both ways and be well underway with station excavation now.