Developer: Rekai Centres
Architect: Montgomery Sisam Architects
  
Address: 55 Eastern Ave, Toronto
Category: Commercial (Retail), Institutional (Health Care)
Status: Pre-ConstructionCompletion: TBD
Height: 183 ft / 55.70 mStoreys: 13 storeys
Project Forum 196 posts
Real Estate Forum
Follow 12 followingUpload 83 photos
Official WebsiteReport Error


Toronto Cherry Place | 55.7m | 13s | Rekai | Montgomery Sisam

Fancy that......only 5 days ahead of an election call..............getting one........yes one........way overdue...........long term care project in Toronto off the ground.

Now about the City-owned sites in Scaborough and on George Street..........and oh the expansion of Providence LTC by :Unity Health......

Ahem...

Oh.....and no permit applications yet for Sinai/Bridgepoint's new facility either.........the one the Premier announced......err....years ago.
 
I saw the plans and I don't recall there being a retail space or if there was, just a cafe, so I think Benjamin Moore might just be donating paint / labour to this project.

There are plans for a testing centre -- maybe a LifeLabs.
IMG_3319.jpeg

There are these two units at ground.
 
It would be kind of wild if of all businesses doing location scouting and demographic breakdowns -that it’s a paint store that lands one of the two spots here. Off the top of my head, a walk-in dermatological clinic would do gangbusters. Cut that 6am line up at Avantderm in half
 
The Toronto & East York CC are discussing traffic changes due to this construction today and the Report to them gives some dates:

The Development and Timeline
Multiplex Construction Canada Ltd. is constructing a 13-storey long-term care facility at 55 Eastern Avenue. The site is located on the west side of Cherry Street, between FrontStreet East and Eastern Avenue. The site is bounded by Eastern Avenue to the north, Cherry Street to the east, Front Street East to the south, and a private business to the west
The major construction activities and associated timeline for the development are described below:
• Excavation and shoring: from February 2025 to June 2025;
• Below grade formwork: from June 2025 to August 2025
;• Above grade formwork: from September 2025 to August 2026;
• Building envelope phase: from March 2026 to December 2026; and
• Interior finishes stage: from April 2026 to July 2027.

SEE: https://www.toronto.ca/legdocs/mmis/2025/te/bgrd/backgroundfile-252920.pdf
 
The Toronto & East York CC are discussing traffic changes due to this construction today and the Report to them gives some dates:

The Development and Timeline
Multiplex Construction Canada Ltd. is constructing a 13-storey long-term care facility at 55 Eastern Avenue. The site is located on the west side of Cherry Street, between FrontStreet East and Eastern Avenue. The site is bounded by Eastern Avenue to the north, Cherry Street to the east, Front Street East to the south, and a private business to the west
The major construction activities and associated timeline for the development are described below:
• Excavation and shoring: from February 2025 to June 2025;
• Below grade formwork: from June 2025 to August 2025
;• Above grade formwork: from September 2025 to August 2026;
• Building envelope phase: from March 2026 to December 2026; and
• Interior finishes stage: from April 2026 to July 2027.

SEE: https://www.toronto.ca/legdocs/mmis/2025/te/bgrd/backgroundfile-252920.pdf

Excellent find. It's a very aggressive schedule but I've met with Rekai and believe they want to get it done ASAP.
 
Although it's a positive that they intend on getting some shovels in the ground soon, I ultimately expect this to take longer than the aforementioned aggressive timeline. Always anticipate construction to take longer than forecasted in our burg.
 