This should be mark from Pre-Construction to Under Construction
Update from the City of Toronto website and should be open to residents by end of 2023
June 21, 2023 Auditor General Report on "City of Toronto’s Modular Housing Initiative: The Need to Balance Fast Delivery with Stronger Management of Contracts and Costs" - based on interview with Toronto Housing Secretariat Abi Bond and her staff,.... Throughout the Auditor General Report - states the delayed 39 Dundalk Drive (formerly 7 Glamorgan Ave) is expected to open July 2023 - one month after the Auditor General Report!
Image from Page 3: https://www.toronto.ca/legdocs/mmis/2023/au/bgrd/backgroundfile-237804.pdf
View attachment 521631
They have had "partial-occupancy" on that site for a few months now - I believe the End of 2023 target is for full-occupancy...June 21, 2023 Auditor General Report on "City of Toronto’s Modular Housing Initiative: The Need to Balance Fast Delivery with Stronger Management of Contracts and Costs" - based on interview with Toronto Housing Secretariat Abi Bond and her staff,.... Throughout the Auditor General Report - states the delayed 39 Dundalk Drive (formerly 7 Glamorgan Ave) is expected to open July 2023 - one month after the Auditor General Report!
Image from Page 3: https://www.toronto.ca/legdocs/mmis/2023/au/bgrd/backgroundfile-237804.pdf
View attachment 521631