Toronto 115 Larchmount | 21.94m | 6s | Hullmark | superkül

Demolition is underway. From Hullmark's IG:



20210209_154713.jpg
20210209_154740.jpg
 
Hullmark's current IG story shows that they've started doing geothermal drilling on site right now.



Quick description of the geothermal system:

The colourful drums on-site contain drill cuttings. Starting in June, drilling will begin on-site for the geothermal system which will improve the energy efficiency of the new building. More info about upcoming work can be found in Construction Notice #2 above - May 17, 2021

 
Just walked past there on a local stroll... big rigs parked there. Will be great to see more mid-rise along this stretch. Can't wait for more such redevelopment action along Eastern, just to the south.
 


Forecasted construction timeline:

• Excavation and shoring: from August 2021 to November 2021;
• Below grade formwork: from December 2021 to March 2022;
• Above grade formwork: from March 2022 to August 2022;
• Building envelope phase: from August 2022 to December 2022; and
• Interior finishes stage: from January 2023 to June 2023.
 