Well the original is long gone....its already been delayed twice i believe??
The latest one i have for mine is August 2015...which to me is IMPOSSIBLE. So im not expecting anything before 2016....
Not sure if anyone else has any opinions on that or has heard anything else?
Did you anybody know about the tile & drywall strike?
On a second note, does anyone know how long it typically takes for the builder to officially register the condo from their past experience? Trying to gauge how long it will take between occupancy and closing.
No set timeframes per say ... but typically an experienced developer on a 'non-problematic' project would take 6-12 months to register a highrise condo after first occupancies
New firm occupancy day is October 4, 2016. I can not understand that strike six weeks, delay almost 12 weeks. What can we do?