Miracle on Yonge (Richmond Hill Centre, Pemberton, 2x 12s, Rafael & Bigauskas)

Meanwhile - thanks for all the photos Klieg - keep'em coming!

You're welcome :)

Here are some more pics from today. Construction appears to have reached ground level for the west building, with the east building following closely behind.

April 30, 2011

DSC01387.jpg


DSC01394.jpg


DSC01398.jpg


DSC01406.jpg
 
June 26, 2011 Update

Work has begun on the third floor of the west building, while construction is underway on the first and second floors of the east building.

DSC01600.jpg


DSC01621.jpg


DSC01637.jpg


DSC01630.jpg


DSC01686.jpg
 
July 23, 2011

Construction for Building A has reached the fourth floor, while work continues on the third floor for Building B. The entrance for the shared lobby is also starting to take shape, as seen below.

DSC01870.jpg


DSC01838.jpg


DSC01816.jpg


DSC01801.jpg
 
I just received a letter from Pemberton yesterday that the tentative occupancy date has been delayed ... once again ... to September 2012. My unit is on the 6th floor of Building A. They've already finished the 4th floor, do they really need another 13mths to finish building the remaining 8 storeys, enclose, pull all the piping and utilities, and finish the interior?!
 
do they really need another 13mths to finish building the remaining 8 storeys, enclose, pull all the piping and utilities, and finish the interior?!

Yes they do .... and you just listed everything that takes the time to complete ~ :)

its pretty common for typical condos to take 2.5 to 3 years from sales to occupancy .... in my case it is taking 4 years due to the size of the building
 
I just received a letter from Pemberton yesterday that the tentative occupancy date has been delayed ... once again ... to September 2012.

Wow, sorry to hear that. That's quite a delay.

I wonder if they've decided to start occupying both buildings at the same time, as Building B's occupancy is set to begin next July. At least, that's what they were saying a few weeks ago...
 
There's been a lot of progress on this site lately, with Building A now at the seventh storey, and Building B at floor six. Here are some pics from Saturday:

August 20, 2011

DSC01924.jpg


DSC01930.jpg


DSC01934.jpg


DSC01942.jpg


DSC01953.jpg


DSC01959.jpg
 
Last edited:
Building A has reached the 11th floor, while Building B is at the 9th. Exterior brickwork has begun on the west side of Building A, and looks very similar to the renderings that have been released thus far.

September 18, 2011:

DSC01999.jpg


DSC02079.jpg


DSC02074.jpg


DSC02064.jpg


DSC02105.jpg
 
As of October 10th, Building A had more or less topped out at 12 storeys, with work beginning on the 11th floor of Building B. There were a lot more bricks this time around, as well :)

October 10, 2011

DSC02132.jpg


DSC02131.jpg


DSC02151.jpg


DSC02173.jpg


DSC02218.jpg
 
Both buildings have now reached a full 12 storeys. There are also a few windows that have appeared on the north side of Building A.

November 5, 2011

DSC02295.jpg


DSC02314.jpg


DSC02327.jpg


DSC02335.jpg


DSC02351.jpg


DSC02390.jpg
 
Train Tracks

Hello,

Does anyone think there might be issues with noise from the train tracks to the west of Building A?
 
Hello,

Does anyone think there might be issues with noise from the train tracks to the west of Building A?

When I was shopping around and came across this development in Spring2010, I also wondered about the noise. so I visited a few times when there were trains going past, both Go and CN. Since there's a Go stop and a fairly-used train crossing @ Langstaff rd, trains slow down and aren't too noisy.
 