Bolton GO is definitely gonna be a struggle, the amount of money that needs to be spent to make it feasible(In my opinion, correct me if I'm wrong)is going to be very high.
Yes and no. We don't know for sure if ML is contemplating 2WAD or simply peak service to Bolton.
The majority of the grade separations along the Bolton line do already have room roughed in for additional track. (From Steeles up through Woodbridge and Kleinburg, not so much unfortunately). That makes the civil work more affordable, provided CPKC will allow those empty separations to be shared.
To add a single track to this line, the cost per km would likely be similar to the Bowmanville extension. Bolton is about 28 kms to Weston, whereas Oshawa to Bowmanville is only about 18 kms. So Bolton would be higher by virtue of greater length.
If 2WAD is being sought, however... further track might be needed, and the price might go much higher.
- Paul