Goals for this year:
Deal and new tracks/construction to extend Midway and Reverse Peak service to Mt Pleasant
Completion of tracks outside West Harbour
Shovels in the ground for Bowmanville
More second track laid down in Toronto and Aurora
At least try to talk to CP about various things
Anyone disagree?
I'd like them to achieve the following goals in 2024:
West Harbour track connection in service.
Double-track between Kennedy and Unionville in service. It's been sitting nearly complete for a few months already, but the hold up is that bridge under the CP line and over Highland Creek. GO probably won't increase off-peak Stouffville frequency yet due to the track restrictions for Ontario Line construction, but we could at least get counter-peak service to Unionville. Evening train service will presumably be restored when that work is done as well.
Quad track through Weston Station in sevice
. Construction is already complete but I don't think it's in service yet.
Double track in Breslau complete
. It is progressing well, looks like it could be done by the end of the year.
Double track in Guelph complete
. It is also well underway, it looks like most of the work needed now is on the western portion from the west side of Downtown to the Hanlon Parkway.
Double track in Acton complete
. This one is just starting, but it seems fairly straightforward so maybe they could finish it within the year. I don't think they're adding a second platform at the station.
Second platform in Georgetown starting construction
. This is required for counter-peak service to Kitchener. They can run 1 train per hour per direction off-peak using the Breslau and Acton sidings (stopping in Acton every 2 hours), but to accommodate counter-peak service encountering the existing 2 tph peak-direction service they need a second pair of passing locations in Guelph and Georgetown. A second through platform a Georgetown was originally planned to be built at the same time as the above three double track segments but it got delayed significantly for some unknown reason.
Double track from Rutherford to Maple starting construction
. Currently double track ends just north of Maple and just south of Rutherford. Rutherford already has a second track that isn't connected to anything, and Maple has a second platform under construction. Work should start in 2024 to connect the double track segments together, creating a 13.5 km section of uninterrupted double track from north of Downsview Park to south of King City. This wouldn't be sufficient for half-hourly off-peak service, but it could allow the 3-hourly Barrie trips to run separately from the hourly Aurora local trains, eliminating the awkward deadhead moves that are currently required to accommodate the Barrie trains. So there would be 1 tph to Aurora, and a separate express train to Barrie every 3 hours.
Second platform at Mount Joy starting construction
. This is required for counter-peak service to Mt Joy.
Restore 15-minute Lakeshore service. In Fall 2021 there was local service every 15 minutes or better from Oakville to Oshawa, but this was cancelled in early 2022. If they find 4tph too restrictive on Lakeshore East due to Ontario Line construction they should at least run 4 tph off-peak from Oakville to Union. One or both of the existing hourly off-peak services could run express to improve travel times between Hamilton and Toronto as well as for transferring Milton bus passengers.
Double track through Kennedy Station designed
. It currently ends just north of the station, and the station has two platforms, but there is no control point on the south side of the station which would allow them to use both platforms. Such a control point should be installed, which will involve some creativity to incorporate the freight siding which is not currently signalled at all. Hopefully they can design it in 2024 and get shovels in the ground by the end of the year.
Quad track through Mount Dennis station designed
. The quad track currently ends north of Mount Dennis pending construction of the fourth (east side) platform, which started construction later than the other three. But with all the days on Line 5 construction, that platform looks like it will be complete around the time of the station opening. So the quad track should be brought through the station to increase the margin of error for trains scheduled to meet on the new quad-tracked section through Weston. I'd like them to get shovels in the ground by the end of 2024.