Some progress pics for Maple GO.
Structure of the new elevator and stair building. North tunnel to both platforms is being backfilled. Foundation and rebar (right side of pic) is in for the last piece of the new retaining wall for the expanded Eagle Rock Way bus loop.
View attachment 429382
West platform south tunnel entrance being built up:
View attachment 429378
Rough grading for 2nd track is completed to about halfway between Maple GO and Rutherford GO:
View attachment 429379
New retaining wall posts are moving steadily north from Rutherford GO, nearing halfway to Maple GO:
View attachment 429380
New retaining walls going in on the west side lagging behind the posts:
View attachment 429381