drum118
Superstar
Oct 04
Lot more up on site. They finally have the maintenance building almost built at the south end of the parking lot near the platform. Most of the east platform is built and working on the east stair to the new underpass.
With the bridge in place over Steeles, track work is underway for track 1 with track to to be place on the bridge after the bridge is seal and ballast. Could be a weekend end in Nov or Dec that will see no service on the line and Steeles close to traffic so the existing line can be place across Steeles and connecting to the tracks on that side. Also shifting of track 2 back in place will take place as well. Once done, then the excavation can start to remove the earth under the bridge for the new underpass.
Once track 2 is shifted back into place, work can get underway for building the stair to the underpass as well the new platform.
Lot more up on site. They finally have the maintenance building almost built at the south end of the parking lot near the platform. Most of the east platform is built and working on the east stair to the new underpass.
With the bridge in place over Steeles, track work is underway for track 1 with track to to be place on the bridge after the bridge is seal and ballast. Could be a weekend end in Nov or Dec that will see no service on the line and Steeles close to traffic so the existing line can be place across Steeles and connecting to the tracks on that side. Also shifting of track 2 back in place will take place as well. Once done, then the excavation can start to remove the earth under the bridge for the new underpass.
Once track 2 is shifted back into place, work can get underway for building the stair to the underpass as well the new platform.