Lane Closures on Steeles Avenue, Starting Monday April 2As part of construction to build a new grade separation to improve safety and reduce congestion at Steeles Avenue, construction crews will perform roadway boreholes on Steeles Avenue East between Kennedy Road and Midland Avenue, and on selected adjacent streets (Redlea Avenue, Old Kennedy Road, Turff Avenue and Silver Star Boulevard). Work will
commence on Monday April 2nd and last for approximately three weeks. The contractor may require additional lane closures in this area in the future. Metrolinx will provide advance notification in this event.
Work Performed/Construction Activities:
- Flagging and signaling at road intersection
- Removing spoiled soil from McNicoll compound
- Observing signal works in bungalows at McNicoll, Passmore and Steels Avenue crossing
- Deep Foundation-Installed 3 noise wall posts in between Marilyn Avenue and Havendale road crossing.
- Bottom tips depths of posts are at 5.4 m below ground level
- Checked and approved soil at bottom tips of noise wall posts
- Carried out field concrete tests and made cylinder samples for laboratory strength tests prior to concrete pour into the post holes.
- Preparatory works in progress prior to start directional drilling works in order to installing utility ducts in between Steeles Avenue and Kennedy road
- Removing locks from the old rail tracks in between Passmore Avenue crossing and McNicoll compound
- An environmental inspection was carried out today. It was recommended that silt fence at both sides of the culver beside McNicoll compound be repositioned straight as well as old straw bales be replaced with fresh one
Work Scheduled for This Week:
- Dewatering
- Snow removal
- Loading and unloading of material
- Delivering ties to St. Clair yard
- Installing NWS posts for bar #11
- Signal work at Passmore
- Double handing of ties and rails
- Destressing of rails