You can see the steel framing that will be support the existing bridges while the wall is knock down until the new supports are built. The north side will see the same thing.
I'm at a lost why concrete columns are been pour in the new underpass. They could be for the centre section to go under the existing bridges or support the forming for the roof.
They are back filling the east side with the centre section strip.
There is no rendering of the underpass on line and I have not seen one. You can go to the contractor shed and ask to see one, but don't hold your breath on it.
You can see the steel framing that will be support the existing bridges while the wall is knock down until the new supports are built. The north side will see the same thing.
I'm at a lost why concrete columns are been pour in the new underpass. They could be for the centre section to go under the existing bridges or support the forming for the roof.
They are back filling the east side with the centre section strip.
There is no rendering of the underpass on line and I have not seen one. You can go to the contractor shed and ask to see one, but don't hold your breath on it.