  1. C

    Toronto Discovery at Concord Park Place | ?m | 28s | Concord Adex | BDP Quadrangle

    Definitely looks good. The question now is WHEN?
  2. C

    Discovery Condos (Concord Park Place) - Real Estate -

    So my next question is can a Final Interim occupancy date legally be delayed by any specified amount of time?
  3. C

    Discovery Condos (Concord Park Place) - Real Estate -

    Now the plot thickens. AKS, you brought up a very valid point but can people who bought into the same building have their final occupancy dates differ by more than a few months? With that being said, Oui_hallo, did you buy a unit on a lower floor? I am a part of Discovery 2 as well...
  4. C

    Discovery Condos (Concord Park Place) - Real Estate -

    Hi OUI_HALLO, Congrats on the new purchase. Thanks for the update. In regards to your close date, did they state that the final interim closing date was Nov 2011? I remember I was at the sales office a few months ago and they showed me a flyer with a summer 2011 completion date for the...
  5. C

    Discovery Condos (Concord Park Place) - Real Estate -

    Well apparently with Tango, there is a stipulation stating that the absolute longest they can delay the project is until Dec 2015. I was told that there are no current problems and it should be on scheduled for 2013 as there are other future buildings with tight deadlines that need to be met.
  6. C

    Discovery Condos (Concord Park Place) - Real Estate -

    If we were all guaranteed that the Concord complex would be officially registered by the final occupancy date then that would definitely be a plus. HOWEVER, I have a feeling that we may still feel the COLD BREEZE of the phantom rent. The builder might decide to wait until all amenities are...
  7. C

    Discovery Condos (Concord Park Place) - Real Estate -

    Well out of fairness, Discovery 1 owners have received their confirmed letters about the January 2012 occupancy. Discovery 2 owners probably won't be moving in until late spring of 2012. Yeah, it is one big royal screw-job with that underground river story. I'm not too sure if I believe it...
  8. C

    Discovery Condos (Concord Park Place) - Real Estate -

    Well.. I got the official answer. I had to wait a few days to calm down before sharing the news. So, I strolled into the sales office on Friday afternoon. The office was quiet dead so it didn't take too long to see a random sales agent. Before, asking the main and most obvious...
  9. C

    Discovery Condos (Concord Park Place) - Real Estate -

    First of all, just want to say welcome to the future neighbours of Aria. I do agree that moving in during last stages of construction can be difficult. However, if you were to take a look at the Concord parkplace complex, you would never suspect it would take another year for completion...
  10. C

    Discovery Condos (Concord Park Place) - Real Estate -

    Also found this article talking about Toronto Condo delays.. Maximum no. of days for occupancy delay for condo Agreement signed on or before June 30, 08 The builder can delay occupancy of a new condominium unit for up to 5 days without giving notice or compensation. Also, compensation...
  11. C

    Discovery Condos (Concord Park Place) - Real Estate -

    Just noticed that the Aria Condos just down the road are pretty much completed. I remember they were in a similar stage where Parkplace was back in May 2010. I don't like to compare and complain but it just seems ridiculous that the external structure of the Concord condos are completed yet...
  12. C

    Discovery Condos (Concord Park Place) - Real Estate -

    I think there must have been some sort of delay as it doesn't take another full year to complete all the amenities. The builder had noted back in early November that they wouldn't complete the entire project until January 2012. Seems a bit odd to finish the complex in the middle of winte...
  13. C

    Discovery Condos (Concord Park Place) - Real Estate -

    This is just horrible news. I expect I will get my letter shortly as well. I thought things were on schedule for June 2011. Don't understand why it would take another year to be finalized. Of course in the mean time, my downpayment is collecting interest in some bank account!
  14. C

    Toronto Discovery at Concord Park Place | ?m | 28s | Concord Adex | BDP Quadrangle

    Nice to see this thread come back to alive for a bit. It is good news to hear that the crane has gone from Building A. I found this article talking about the construction. By completion of the entire phase I assume all the amenities. http://dcnonl.com/article/id41294
  15. C

    Discovery Condos (Concord Park Place) - Real Estate -

    I hear the builder has a scheduled completion for all facilities in the complex set at January 2012. So if you have to take occupancy by June 2011, there may be a full 6 months before all the amenities are ready for use
  16. C

    Toronto Discovery at Concord Park Place | ?m | 28s | Concord Adex | BDP Quadrangle

    Great pics!!! I am located in Building D. Since buildings A+B have been delayed till June 2011, I can only assume building D+E will be delayed till Dec 2011. Still wondering why it would take another 16 months to complete a building (D) when it only has about 12 floors.
  17. C

    Toronto Discovery at Concord Park Place | ?m | 28s | Concord Adex | BDP Quadrangle

    What about the pics for the often forgotten and beloved building D?? That's where I will be. I heard it should be on the same pace with Building E.
  18. C

    Toronto Discovery at Concord Park Place | ?m | 28s | Concord Adex | BDP Quadrangle

    Does anyone know if construction is still on schedule with Buildings A & B to be completed by December of 2010 and Buildings D & E to be ready by June 30, 2011?
  19. C

    Discovery Condos (Concord Park Place) - Real Estate -

    Hey, Well i went by the sales office 2 days ago. I pretended to be a secret undercover buyer. Building A and Building B are scheduled to be completed by December 2010 Assuming that there are no delays with Discovery 1, Discovery 2 (Building D + E) will be up 6 to 8 months afterwards...
  20. C

    Discovery Condos (Concord Park Place) - Real Estate -

    Hi all, I also bought a unit from Concord Parkplace. I am in building D. I went by the office the other day and i was told that my building won't be ready until December 2011.