tnarduzzi
Active Member
According City of Toronto staff that I spoke to today in Bay:
Yet, as it stands the only other way to connect directly to the TTC is via the diversion/bypass near the old LCBO. The glass roof atriums might still be a long way off, but if you ask me they had better hurry up work on the Front Street Centre Moat... winter is coming.
The Bay concourse is slated to close and demolition begin during the first week of September. (By close they are referring to the remaining bit connecting to the TTC.) The remaining fittings are currently being removed. Hoardings will be installed isolating Bay concourse from the rest of Union and interior demolition will begin in preparation for the underpinning.
Yet, as it stands the only other way to connect directly to the TTC is via the diversion/bypass near the old LCBO. The glass roof atriums might still be a long way off, but if you ask me they had better hurry up work on the Front Street Centre Moat... winter is coming.