crs1026
Superstar
Do I think that? No.Do you really think that this whole project could be completed in 2-3 years? For example, if the plan is indeed to replace the swing bridge, it would take a year for the RFQ on the new design, a a year or two to finalize the design, a year for the RFQ on the construction and a couple years to build the replacement.
Is that what VIA claimed was possible? Yes.
Six years is a change from the stated plan, which iirc was closer to 4.
Shame on us for relying on the little that has been said about this project publicly.
- Paul