Excellent info, as always
@Urban Sky
Questions(s). for you, or
@reaperexpress
1) Working with the existing infrastructure and freight schedules is there theoretical room for any additional slots for VIA, within the desirable time ranges that could be negotiated wiht CN/CP, in theory?
2) If not, what is the lowest level of infrastructure investment that would be required to open up new slots, (passing track, rail to rail grade separations, switches/turnounts, etc) and would there be any credible case for the investment, when considering dollars to sustained revenue/service gain
3) Would any of the above investments overlap, to a high certainty with any HSR plan, such that they could be considered an 'early work' advancing the later.
4) Finally, is there 'room' and any logic, to using a portion of the existing CP mainline (Bellevillle) route to bypass any congestion in the CN corridor for even a couple of slots a day? There are multiple crossings/connections between Oshsawa and Belleville.