the contract with ELM to complete is 24 months once they start ..I can't believe this. But it seems like it is too good to be true. I think, For now, they plan to move the outside occupancy date to 2028. Once that’s settled and everyone believes the price won’t change, they will likely adjust the price around 2027 or closer to the occupancy date.
I feel like some trap is here.
In addition to the construction management fee, Elm is eligible to earn certainincentive bonuses including:i. a bonus of 15% of the amount by which the total Division 1-16 constructionhard costs to the total completion of the Project are less than$100,000,000.00; andii. three scheduled based incentive payments of $200,000.00 each percertain occupancy related milestone dates.f) Schedule: the schedule assumes that the construction will commence promptlyfollowing Court-approval with a completion target date of 24 months.