What they should do is fix the Missing Link and then run GO Trains from Milton to Markham that stop at the Toronto North Station which is currently an LCBO. This will give people direct GO Train access to Bloor and Yonge Area. I know its at Summerhill but people can quickly get on the Subway and go to Yonge-Bloor or go uptown to Yonge-St.Clair which will spur job growth in both areas.
Didn’t know there was a North Toronto station that’s been abandoned. Definitely makes sense, and the proximity to the new Crosstown will hopefully rivitalize the midtown area and have large business throughout the region, rather than all cramming into the downtown core.
 

DSC

Superstar
Member Bio
Joined
Jan 13, 2008
Messages
14,166
Reaction score
12,898
Location
St Lawrence Market Area
Didn’t know there was a North Toronto station that’s been abandoned. Definitely makes sense, and the proximity to the new Crosstown will hopefully rivitalize the midtown area and have large business throughout the region, rather than all cramming into the downtown core.
AFIK, the 'north Toronto station' does not really exist any more (either as a building that could be used - it is now an LCBO) or with platforms (which were removed decades ago). The rail line is now the main freight line through Toronto (there is now negligible freight traffic passing through the Union Station Rail Corridor.)
 

EnviroTO

Senior Member
Member Bio
Joined
Apr 22, 2007
Messages
4,358
Reaction score
1,201
Location
Yonge & Mt.Pleasant
I'm sure the effort to turn North Toronto Station into a functioning GO station is not that difficult if that is what the province wanted to do, as compared to new build options in a different location on the line. The greater effort would be the investment required on track infrastructure to remove the contention with freight traffic (i.e. new passenger only rails on the south side of the corridor or a Toronto bypass).
 

Northern Light

Superstar
Member Bio
Joined
May 20, 2007
Messages
16,657
Reaction score
35,628
Location
Toronto/EY
AFIK, the 'north Toronto station' does not really exist any more (either as a building that could be used - it is now an LCBO) or with platforms (which were removed decades ago). The rail line is now the main freight line through Toronto (there is now negligible freight traffic passing through the Union Station Rail Corridor.)
I'm sure the effort to turn North Toronto Station into a functioning GO station is not that difficult if that is what the province wanted to do, as compared to new build options in a different location on the line. The greater effort would be the investment required on track infrastructure to remove the contention with freight traffic (i.e. new passenger only rails on the south side of the corridor or a Toronto bypass).

A couple of things to mention here.

The LCBO is occupying the original station, which has been lovingly restored. The restoration was done with an eye to preserving the option of restoring passenger service in the future.

The stairs to the platforms are still intact, preserved behind walls, and covered up top.

1638404762346.png

from: https://globalnews.ca/news/1510531/what-you-might-not-know-about-the-summerhill-lcbo/

***

Space for the platforms is mostly intact:

1638404936331.png


Though the LCBO did build into that space somewhat

****

Overall, subject to losing one of the great booze barns on earth.........returning the station to active service would be remarkably straight-forward.

As noted by @EnviroTO , the greater challenge would lie in both obtaining CP's blessing to run the service, and the requisite infrastructure investments (added track, upgraded signalling etc.) that would be required.

However, it's my understanding that CP is in fact open to this idea, provided the province brings the $$$.

I think it's likely it will happen at some point...........but

It's far from a current priority...........I certainly don't expect any investment here in the next decade.
 

Woodbridge_Heights

Senior Member
Member Bio
Joined
Feb 14, 2008
Messages
3,022
Reaction score
934
15 years ago the rail deck park was an urbanist's pipe dream, now we are seeing it coming together ... s l o w l y ...

I wouldn't be surprised to see a mid town line centred on North Toronto come to fruition during the 2050's

I personally think the main rail hubs in Toronto should be Union, Pearson Transit hub, Dundas Wes/Lansdowne, and North Toronto/Midtown. Secondary/Tertiary hubs (mainly due to connectivity/distance issues) would be Kipling, Danforth/Main, and Kennedy.
 

Richard White

Senior Member
Member Bio
Joined
Dec 7, 2015
Messages
4,633
Reaction score
2,901
Location
Scarborough, Ontario
15 years ago the rail deck park was an urbanist's pipe dream, now we are seeing it coming together ... s l o w l y ...

I wouldn't be surprised to see a mid town line centred on North Toronto come to fruition during the 2050's

I personally think the main rail hubs in Toronto should be Union, Pearson Transit hub, Dundas Wes/Lansdowne, and North Toronto/Midtown. Secondary/Tertiary hubs (mainly due to connectivity/distance issues) would be Kipling, Danforth/Main, and Kennedy.

Guildwood would be a better railway hub than Kennedy or Danforth. During the G20, it was the defacto terminal for trains coming from the east.
 

DSC

Superstar
Member Bio
Joined
Jan 13, 2008
Messages
14,166
Reaction score
12,898
Location
St Lawrence Market Area
What's with the east front doors (@ Bay) being blocked off with orange tarps. I assumed these were put there (about 4-5 months ago) to allow them to repair/replace the older doors (as they did with the centre doors) but it seems to be VERY slow (even for Union!) Possibly they have taken them off and sent them somewhere to be refurbished? (I assume the west doors - to UPX - will be done next (and last).
 

wopchop

Building Toronto
Member Bio
Joined
Mar 28, 2011
Messages
1,562
Reaction score
568
Location
Oakville
What's with the east front doors (@ Bay) being blocked off with orange tarps. I assumed these were put there (about 4-5 months ago) to allow them to repair/replace the older doors (as they did with the centre doors) but it seems to be VERY slow (even for Union!) Possibly they have taken them off and sent them somewhere to be refurbished? (I assume the west doors - to UPX - will be done next (and last).
Possibly struggling with supply chain like everyone else.
The current PVDF resin shortage means you cannot get painted aluminium extrusion for the doors.
Shipping backlogs delaying hardware shipments. A lot of door hardware is imported.
Steel shortages also affect hardware.
Some door security hardware requires chips.
Polyamides for thermal breaks are in high demand too.
 

Northern Light

Superstar
Member Bio
Joined
May 20, 2007
Messages
16,657
Reaction score
35,628
Location
Toronto/EY
Possibly struggling with supply chain like everyone else.
The current PVDF resin shortage means you cannot get painted aluminium extrusion for the doors.
Shipping backlogs delaying hardware shipments. A lot of door hardware is imported.
Steel shortages also affect hardware.
Some door security hardware requires chips.
Polyamides for thermal breaks are in high demand too.

Wopchop isn't just a pretty face; he's full of interesting info! TY!
 

wopchop

Building Toronto
Member Bio
Joined
Mar 28, 2011
Messages
1,562
Reaction score
568
Location
Oakville
Wopchop isn't just a pretty face; he's full of interesting info! TY!
No problem.
I don't even know if those doors are painted, or if they were stainless, or what they are doing really. But those are all real issues that suppliers are experiencing right now. There are hundreds more.

I am sure we have all walked by a site and wondered why everything takes forever.
Passing judgement is easy.
Understanding is hard.
 

DSC

Superstar
Member Bio
Joined
Jan 13, 2008
Messages
14,166
Reaction score
12,898
Location
St Lawrence Market Area
No problem.
I don't even know if those doors are painted, or if they were stainless, or what they are doing really. But those are all real issues that suppliers are experiencing right now. There are hundreds more.

I am sure we have all walked by a site and wondered why everything takes forever.
Passing judgement is easy.
Understanding is hard.
Agreed, but (on all their projects) the City would stop much criticism if they actually explained what they are doing and their schedule. Shit DOES happen and there is no doubt that getting 'stuff' currently takes far too long. The City has a website on Union Station renovation/restoration ( https://www.toronto.ca/services-pay...tion/union-station-revitalization-milestones/ ) which says 'the revitalization of Union Station concluded in July 2021" - which is clearly untrue! They have announced that the Great Hall floor and lighting will be fixed in 2022 and the ceiling of the area below the Great Hall will be painted in Q1 2022.
 

wopchop

Building Toronto
Member Bio
Joined
Mar 28, 2011
Messages
1,562
Reaction score
568
Location
Oakville
Not going to defend the City, but people take the announcement of completion far too literally.

More than likely they announced it was completed because the contract achieved "substantial completion".

This is a contractual term, which means that the property is fit for occupancy, the municipality issues Occupancy Permit, and the Owner or Tenant can take possession.
It does not mean than 100% of the work is completed. Not by a longshot in many cases.

I have worked many, many projects that achieved SC and has plenty of work left to achieve substantial performance of the contract.
 
Last edited:

trtcttc

New Member
Member Bio
Joined
Aug 15, 2019
Messages
86
Reaction score
323
Not going to defend the City, but people take the announcement of completion far too literally.

More than likely they announced it was completed because the contract achieved "substantial completion".

This is a contractual term, which means that the property is fit for occupancy, the municipality issues Occupancy Permit, and the Owner or Tenant can take possession.
It does not mean than 100% of the work is completed. Not by a longshot in many cases.

I have worked many, many projects that achieved SC and has plenty of work left to achieve substantial performance of the contract.
Have no issue with celebrating SC on the contract, but maybe they should hold an office party for that and not announce it to everyone. It’s not just small work left, if I walked through a station with hoarding everywhere, major passageway closed, most of the food and retail not yet open, I don’t know how I’d consider that renovation completed.
 

wopchop

Building Toronto
Member Bio
Joined
Mar 28, 2011
Messages
1,562
Reaction score
568
Location
Oakville
Have no issue with celebrating SC on the contract, but maybe they should hold an office party for that and not announce it to everyone. It’s not just small work left, if I walked through a station with hoarding everywhere, major passageway closed, most of the food and retail not yet open, I don’t know how I’d consider that renovation completed.
I mostly agree. Politicians and Metrolinx love any chance to peacock in front of us.
But I believe a lot of hoarding has to do with retail fit out, which has nothing to do with the city contract. Those would be done by whomever is leasing the spaces.
Those spaces could be empty for years. Does that mean the station is not done for years because no one rented some spaces?
Of course not, that would be ridiculous.
 