The Final version of the Master Plan heads to the next meeting of Infrastructure and Environment Ctte:
Report:
Plan Part 1:
https://www.toronto.ca/legdocs/mmis/2024/ie/bgrd/backgroundfile-246911.pdf
Plan Part 2:
https://www.toronto.ca/legdocs/mmis/2024/ie/bgrd/backgroundfile-247007.pdf
The substance, such as it is, can be found in Part 2, which includes 'implementation' and demonstrations.
That substance begins at p.139 of the Consultant Enrichment Program produced document.
****
First a note on what's in the plan, such as it is............. a fair bit of good stuff actually.......... though only a small fraction is likely to be delivered in the next decade. The list so far exceeds budget, laughable isn't even the word.
I won't even bother doing the math, except to say, the wish list, done properly far exceeds 500M (new Ferry Terminal, expansion of Harbour Square Park, New Gateway at the Centre Island Ferry Dock and a lot more)
If you remove money from the Ferry project, and essential state-of-good-repair............you get 23.2M for the Masterplan over the next decade.
At that pace, you would spend up to ~60M in today's money over the 25-year life of the plan, which would deliver, at most 15% of the wish list. A futile exercise without vastly more funding.
*****
FWIW.........here's my first move, nix Rees Park for now........take the entire budget and move it to Harbour Square Park and the Ferry Terminal, do those projects (including Park Expansion, and do them properly, no VE'ing).
Sadly, I think we'll do a VE'd effort over at Rees, and not much at all elsewhere....
Holy @#$#, I feel like I'm channeling
@allengeorge