Toronto The Well | 174.03m | 46s | RioCan | Hariri Pontarini

Dec 12, 2021

4F565013-FD4E-470E-B559-1DF2195B4A6F_1_201_a.jpeg



AC069F22-17FB-43C8-A0B4-46F9D74C36A4_1_201_a.jpeg



9DC59828-68A7-4ED8-9E4A-1761939B1292_1_201_a.jpeg



4BF19611-5F23-4D47-AF8E-42DE9170A9B5_1_201_a.jpeg



7888E457-06CF-47F7-8241-E415F01A53E9_1_201_a.jpeg



2B8E7C40-5C29-4D2E-80AD-772560136C53_1_201_a.jpeg



2C93F255-A060-41AC-9E27-1581CD6FEC22_1_201_a.jpeg



CD077F9E-7FA4-42CA-94DA-97C248396B07_1_201_a.jpeg



7AD49EF6-0170-478E-9558-02D22B798A34_1_201_a.jpeg



194595D1-DBD2-449A-AA78-1D57E9A1F847_1_201_a.jpeg



929B70F1-243B-4AF4-9F75-B4DAA1BB3041_1_201_a.jpeg



3123D6D6-79A0-407A-BB36-C2AA5EA2F92D_1_201_a.jpeg



4659DA9E-EBE3-4CC6-92DA-B45EAD265A76_1_201_a.jpeg
 
The Well in the Sunday afternoon sunshine. Looks like only two window sections to be installed on the top floor office tower to complete its enclosing. After that, replacement of several absent or damaged pieces where the missing sections are currently boarded up - primarily on the office tower's south facing wall.

20211219_163251.jpg
 
Kinda makes me wonder what they're doing within all that intense scaffolding.
 
December 23, 2021: MAJOR MILESTONE - The Well office tower is now completely enclosed.

The final two window sections of the west facade, where the construction hoist openings used to be, were installed in the past few minutes this morning - almost exactly five full years since the RioCan, Allied, Diamond partnership (RAD) took vacant possession of the former Globe lands site on January 1, 2017. Only the rooftop perimeter railing section left to complete.

20211223_104229.jpg
 