Just read about that. SKYGRid to take over project.
Just read about that. SKYGRid to take over project.
Given the Receiver in charge of this project now, this was very predictable and not surprising in the least. I am sure we will now witness some degradation in how this building is fitted out, and the projects final completion. Should be interesting to see how this further unfolds. I am sure there will be more to come as a sale process continues.Just read about that. SKYGRid to take over project.
Many were surprised when Mizrahi, a relatively inexperienced developer, revealed plans for what was supposed to be the second-tallest man-made structure in the country almost 10 years ago.
In the decade since, the project has lurched through a series of mishaps and pitfalls, including noise complaints, permitting failures, financing woes, cost overruns and partnership breakdowns.
Tl,dr: Seems like Sam was getting in the way and therefore, was sent a packing...
...didn't help he was trying to sue the receivership hand that was helping him from what I gather from that TorStar article. That's kinda embarrassing really. /sigh
I'm pretty sure that was a misquote on the writer's part.
Mizrahi pushed out of The One skyscraper development — inside details of what he told employees
“For me, it’s just mind boggling,” Mizrahi Developments founder Sam Mizrahi said in recording obtained by the Star. “I don’t see how somebody else is going to do it better than we are.”www.thestar.com
Excerpts from the article:
“We just have a difference of opinion on how to build this building,” he continued. “I like to build stuff that's the top quality and the best there is … and they want take it in a different direction.”
And
Mizrahi confirmed the news to the Star late afternoon on Monday. “We just have a different vision for how I want to finish the building versus what's going to happen,” he said. “That created an impasse.”
This sounds like there is going to be cheapening going forward . I hope the cladding at least stays the same. They can’t put up cheeper material on the top part at this stage right?
It would kind of be funny if the building ended up only be built to the 75 stories that was proposed when the project first broke groundThough the height increase is tied to additional benefits the city secured. If the receivership doesn’t want to commit to that deal, there’s no height increase. This could be the impasse.
More floors means more units to sell with disproportionately lower cost. This is why all developers lobby for more floors. The way I read this is that that the receiver wants to cut costs by using cheaper interiors while Mizrahi thinks that will cheapen the building and thus you can’t expect to charge “luxury” prices.Though the height increase is tied to additional benefits the city secured. If the receivership doesn’t want to commit to that deal, there’s no height increase. This could be the impasse.
It seems that the scale of this project was above Sam's ability from the beginning. When you start building without the proper permits and the project comes to a standstill for months on end due to not having permits in place is not the way to build a project on time or on budget.
I have been in the building industry for more then 40 years and a project of this scale and complexity has to be run by a seasoned GC that can organize and deliver on time and unfortunately he thought that he could accomplish this.
I give him credit for the vision of creating an incredible building.
I kind of read it with the cost and overruns thing that it's possible that materials were back ordered or delayed and that Sam was not willing or could not source new materials to fill the void causing delays. Just kind of how I read itMore floors means more units to sell with disproportionately lower cost. This is why all developers lobby for more floors. The way I read this is that that the receiver wants to cut costs by using cheaper interiors while Mizrahi thinks that will cheapen the building and thus you can’t expect to charge “luxury” prices.
I do not foresee any change in exterior cladding. That wouldn't make any sense.
There isn't likely a huge savings to be had with 'internal' cheapening either, given that there are contracted units which will have a fair bit of specificity on finish.
I suppose one could lower the fit and finish of interior common areas, but it really doesn't seem likely.
I think @Tuscani01 is more likely to be on point. I can think of one or two other things that could come up, but his is the best explanation, I think. But we'll have to see!
SkyGrid this morningThe way I read this is that that the receiver wants to cut costs by using cheaper interiors while Mizrahi thinks that will cheapen the building and thus you can’t expect to charge “luxury” prices.