I think we (I?) need an official floor counter. I never have a clue what floor they're on, aside from being reasonably sure for about two weeks after someone happens to announce it.
You're absolutely right, I think it would be much appreciated here to give everyone another nugget of The One progress goodness.I think we (I?) need an official floor counter. I never have a clue what floor they're on, aside from being reasonably sure for about two weeks after someone happens to announce it.
I concur. I think they were pouring the walls in #14,305.You're absolutely right, I think it would be much appreciated here to give everyone another nugget of The One progress goodness.
After doing some sleuthing through the past posts on this thread I can give my best approximation of the last few floors:
Feb. 28 - 22nd floor slab complete
March 11 - 23rd floor slab complete
March 22 - 24th floor slab complete
So my best guess would be that they have poured the walls of the 24th floor and are setting up the formwork for the 25th floor slab.
No, clearly the field is shadowed by floors 85 to 95 of The One.This perfectly shows the relative location of the One to the school/park in the foreground. The pic must’ve been in late afternoon because the field is in the shadows of the few mid rises to the east.