Former Cresford Developments president alleges ‘cash crisis’ at condo firm
SHANE DINGMAN REAL ESTATE REPORTER
SHANE DINGMAN REAL ESTATE REPORTER
The filing describes escalating construction costs for key inputs such as steel and concrete beginning in the fall of 2018. Ms. Athanasoulis said the Clover project was facing $50-million in extra costs, at the same time the Halo project faced overruns close to $45-million. The lawsuit cites a third-party review by cost consultants CB Ross that is said to show 33 Yorkville’s budget needed another $65-million. Some of those bills were paid, but others remained outstanding.
Former Cresford Developments president alleges ‘cash crisis’ at condo firm
A 33-page wrongful dismissal complaint filed on Jan. 21 by Maria Athanasoulis alleges Cresford Developments is failing to pay contractors and incurring costly delays on its projects
www.theglobeandmail.com