The Development and Timeline
A 14-storey residential building is being constructed by CentreCourt Development at 859-861 and 875 Eglinton Avenue West. The site is bounded by Eglinton Avenue West to the north, Bathurst Street to the east, a commercial two-storey building (2016 Bathurst Street) and public laneway to the south and Peveril Hill North to the west. The development, in its completed form, will consist of 333 dwelling units with ground-floor retail and a two-level underground parking garage for approximately 201 vehicles.
A detailed review of the construction schedule was undertaken by the developer to minimize the project duration and impacts of the construction on all road users. Based on the information provided by the developer, the entire site will be excavated lot line to lot line on all four sides. The developer has advised that due to limited availability of space, all construction activities, including delivery and storage of construction materials, cannot be accommodated within the site.
Major construction activities and associated timelines for the development are described below:
• Demolition: December 2020 to January 2021;
• Excavation and shoring: January 2021 to August 2021;
• Below grade formwork: June 2021 to February 2022;
• Above grade formwork: February 2022 to January 2023;
• Building envelope phase: December 2021 to April 2023; and
• Interior finishes stage: February 2022 to August 2023.
A construction staging area will be set up within the road right-of-way including the east sidewalk and the entire roadway of Peveril Hill North between Eglinton Avenue West and the first laneway south of Eglinton Avenue West for a period of 29 months.