Toronto TeaGarden Condos | 51.45m | 15s | Phantom | Kirkor

Super slow build.
20220128_104442.jpg
20220128_104548.jpg
 
Boy was I wrong on the topping off date for this building as it going to later than it should be. I did say in June it maybe top off by Nov or end of the year, but looks like end of March now.

They are only doing the 10th floor now. Was planning on shoot it this week and was expecting a top off tower.

This has been a painful project to follow.
 
Boy was I wrong on the topping off date for this building as it going to later than it should be. I did say in June it maybe top off by Nov or end of the year, but looks like end of March now.

They are only doing the 10th floor now. Was planning on shoot it this week and was expecting a top off tower.

This has been a painful project to follow.
Might even take till June who knows. Super slow build.
 
Might even take till June who knows. Super slow build.
This is the slowest of any projects I have shot the last 12 years and you maybe right. Costing someone money to carry this project way past it should be completion date for last year.

Wondering what kind of line they handing to the buyers for this delay?
 
This is the slowest of any projects I have shot the last 12 years and you maybe right. Costing someone money to carry this project way past it should be completion date for last year.

Wondering what kind of line they handing to the buyers for this delay?
Screenshot_20220225-085526_Chrome.jpg
Screenshot_20220225-085536_Chrome.jpg
 
Feb 27
Forming is taking place on the 10th floor with 2 more floors and the Mech floor to go. By standard, this building will be top off by the end of March and months late.

According to Phantom site for this project, they are still calling for 2022 move-in date and well before the May 2024 as noted in the letter. Unless the 2024 date is a typo, this is a scare tactic to get current buyer to cancel so Phantom can resale them at greater price that will not only cover the $16,000 buyout, cost of everything and a higher profit return.

I stand to be corrected, but looks like someone else is funding this project now.

Which project have I not seen with these panels being install on? In fact I saw the same colour and style on another project that I shot later after this one.

More up on my site
51910871201_8840da8f50_b.jpg

51911189814_cbd9c68cc4_b.jpg

51909903512_82d4dd93d2_b.jpg

51911189449_e435fbf7d3_b.jpg

51911489810_c31d00d364_b.jpg

51911189304_9e09c5f33c_b.jpg

51909903107_f8acfda8e6_b.jpg

51909902982_2e4a5c3354_b.jpg

51910966128_d736d482df_b.jpg

51911489165_66838ba371_b.jpg
 
Feb 27
Forming is taking place on the 10th floor with 2 more floors and the Mech floor to go. By standard, this building will be top off by the end of March and months late.

According to Phantom site for this project, they are still calling for 2022 move-in date and well before the May 2024 as noted in the letter. Unless the 2024 date is a typo, this is a scare tactic to get current buyer to cancel so Phantom can resale them at greater price that will not only cover the $16,000 buyout, cost of everything and a higher profit return.

I stand to be corrected, but looks like someone else is funding this project now.

Which project have I not seen with these panels being install on? In fact I saw the same colour and style on another project that I shot later after this one.

More up on my site
51910871201_8840da8f50_b.jpg

51911189814_cbd9c68cc4_b.jpg

51909903512_82d4dd93d2_b.jpg

51911189449_e435fbf7d3_b.jpg

51911489810_c31d00d364_b.jpg

51911189304_9e09c5f33c_b.jpg

51909903107_f8acfda8e6_b.jpg

51909902982_2e4a5c3354_b.jpg

51910966128_d736d482df_b.jpg

51911489165_66838ba371_b.jpg
Isn't the building suppose to be 14 floors? I might be wrong.
 
Isn't the building suppose to be 14 floors? I might be wrong.
I seen it as 14 floors, but UT has it still listed as 12. If 14 floors, it will be mid April for top off.
 
I seen it as 14 floors, but UT has it still listed as 12. If 14 floors, it will be mid April for top off.
We have had it as 12 storeys as no-one's kept track of the resubmission, appeal to the OLT, and subsequent settlement en route to the hearing. It turns out that there was a 1-day settlement hearing back in October and a Decision released in November that ratifies the settlement. So, the developer is allowed to add 3 more storeys. For whatever reason, the City has considered this an 11-storey project up until now, and now considers it a 14-storey one, but there are amenity spaces on the level above the last floor of suites, so we consider this a 15-storey building…

…of course the building will actually appear to be 16 storeys tall when viewed from Bayview Avenue, as there are two-floor loft units that wrap the P1 garage level facing north and east. Ground floor is one level higher along Teagarden Court though, hence the ignoring of another floor and another approximately 4 metres in height because of the sloping lot.

Anyway… new figures are in the database file and the thread title.

42
 
We have had it as 12 storeys as no-one's kept track of the resubmission, appeal to the OLT, and subsequent settlement en route to the hearing. It turns out that there was a 1-day settlement hearing back in October and a Decision released in November that ratifies the settlement. So, the developer is allowed to add 3 more storeys. For whatever reason, the City has considered this an 11-storey project up until now, and now considers it a 14-storey one, but there are amenity spaces on the level above the last floor of suites, so we consider this a 15-storey building…

…of course the building will actually appear to be 16 storeys tall when viewed from Bayview Avenue, as there are two-floor loft units that wrap the P1 garage level facing north and east. Ground floor is one level higher along Teagarden Court though, hence the ignoring of another floor and another approximately 4 metres in height because of the sloping lot.

Anyway… new figures are in the database file and the thread title.

42
Thanks

One could say the rear count as a floor as it has windows on the rear, east side and part of the south side
 
April 04

They are currently working on the 12th floor with 3 more + mech to come. For the record 15 Floors plus mech

On Feb 25, they were working on the 10th floor. Looks like a floor every 2-3 weeks and it puts it on schedule to be top late June.

Precast panel on an flat deck for placing and looks like all white.
51988435542_c20810e531_b.jpg

51989724139_01a9dc7be6_b.jpg

51989724189_c455bfbe77_b.jpg

51989724214_13df528ec1_b.jpg

51989724369_ed44f77ced_b.jpg

51989997355_aabfbf7d0e_b.jpg

51989439986_73cbf0e404_b.jpg
 
Isn't this project launched sometime in 2015? Surprised seeing it still being built. It's not even a 50 story building...
 

Back
Top