A couple of phone snaps from Wednesday evening
We are probably not going to see this poor until sometime next weekLast posted showing the rebar still had about a third of the slab to be tied
I'm trying to recall all the massive pours we've had in the past and I'm coming up with Four Seasons raft slab and One Bloor raft slab. Transfer slabs at Sugar Wharf were also large but nowhere near as big as those other two.
One Bloor East? One Bloor W had a massive slab pour at the bottom of the pit from what I recall - and as Khaldoon mentioned, so did the Well.I'm trying to recall all the massive pours we've had in the past and I'm coming up with Four Seasons raft slab and One Bloor raft slab. Transfer slabs at Sugar Wharf were also large but nowhere near as big as those other two.
I think the transfer parts where also built into the above grade complex structure of the bottom part of The One. Likely one of the main reasons why it seemingly took forever and a dog's age to get past the 8th floor.One Bloor East? One Bloor W had a massive slab pour at the bottom of the pit from what I recall - and as Khaldoon mentioned, so did the Well.