Second crane should be here any day now.
As part of ongoing construction of the Ontario Line, crews will be installing the second of two tower cranes in the station shaft to support construction at the future Moss Park station. Crews are currently preparing for the installation of the second tower crane within the shaft. This work involves creating a platform area where the crane will be installed directly within the reinforced steel (rebar) structure. The rebar acts as a strong framework that, once filled with concrete, will provide a stable foundation to safely support the tower crane structure.
The delivery of the tower crane components to site is anticipated for mid-October 2025, with installation on-site to follow. The tower crane is expected to be operational as early as mid-November 2025 (after assembly and testing period).