Ontario Line
The Ontario Line was previously reported as a single project with a price tag of over $10 billion. In the Fall 2019 update, the intent was to have the financial close in Winter/Spring 2022 ahead of the election. In the Winter 2020 update, this changed to Spring 2022.
In the Spring 2020 update, the project has been split into separate parts to reflect industry feedback about the original scope.
- GO Corridor from Don River to Gerrard
- South Tunnels, Civil Works and Stations CNE to Don River
- Rolling Stock, System Operations & Maintenance
- North Tunnels, Civil Works and Stations
The GO corridor work will be done as a conventional procurement by Metrolinx and will be bundled with upgrades to GO Transit trackage.
The financial close for items 2 and 3 above is now Fall 2022, and for item 4 it is Fall 2023.
This means that an actual sign-on-the-dotted-line commitment to the project will not be within the current government’s mandate. Even the so-called “early works” comprising the southern portion of the route from Exhibition to the Don River is not scheduled to close until Fall 2022. The northern portion, from Gerrard to Eglinton will close in Fall 2023. This contract is being held back pending results for the south contract to determine the industry’s appetite for the work.
The southern portion, with a long tunnel through downtown and stations in congested street locations would start first. However, the line cannot actually open without the northern portion because this provides the link to the maintenance facility which is included as part of item 3 above although the actual access connection would be built as part of item 4.
An issue linking all of these projects is the choice of technology which, in turn drives decisions such as tunnel and station sizes, power supply, signalling and maintenance facility design. When the Ontario Line was a single project, Metrolinx could say that this choice was up to the bidders, but now there must be some co-ordination to ensure that what is built can actually be used to operate the selected technology. It is hardly a secret that Metrolinx is promoting a SkyTrain like technology, although which propulsion scheme (LIM vs rotary motors) is not clear. There are well-known problems with LIMs and the power pickup technology used on the SRT, and this would also be a consideration for the outdoor portions of the Ontario Line.