rbt
Senior Member
I really appreciate your positivity. The Ontario line is by no means a perfect project but at least we're moving at a faster pace than the Relief line.
Not quite. TTC was ready to place TBM orders 2 years ago. They would have been well into launch pit excavation by now.
AFAIK the Ontario line is still deciding how big the tunnel should be; it's of the answers the selected vendor will provide in ~24 months (6 months to go through RFQ, 12 months to go through RFP, and 6 months for vendor to submit their 5% design).
This is a good step. Still a good 2 years behind where the Relief line process was and 4 years behind where it would have been if funded. Also, Metrolinx would have finished the Relief Line north EA by now with selected routing to Sheppard (if that made economic sense).