There was construction long before the Caisse became involved. To use a local example, that's like trying to claim 407 construction didn't take place until 1990/91 when 407 ETR was formed, when work had actually started in 1987 as a traditional highway.Corrections:
Jan 2015 - The partnership between the public government was announced
April 2016 - The REM was announced publicly
June 2016 - Request for qualification starts
Jan 2018 - tender process ends
April 2018 construction groundbreaking
Dec 2020 train and door testing starts on the 3.5km 'representative segment'
What we can agree on though, is that surface/overhead is very much faster than underground - with the REM LRT approaching the same kind of construction speeds we've seen here on the SRT, Finch West LRT, and Union-Pearson spur. SRT was indeed 1980s, but the other two are both 21st century and faster.