I went on the Ontario Line page on the Metrolinx engage website to check for any updates and there are a few things to note:
Last time, Metrolinx stated that the site of the MSF was unknown despite stating that the IBC mentioning the MSF will be located at Wicksteed Avenue and Beth Nealson Drive. Now it looks like Metrolinx will go forward with the Wicksteed and Beth Nealson location.
View attachment 266284
Next, someone asked if the line was still on schedule for 2027. Metrolinx noted that the 2019 provincial budget contemplated a completion date as early as 2027. But the actual start of construction and completion date would depend on the consortiums who will bid on the project. So don't expect the line to open in 2027. Unless a miracle happens.
View attachment 266285
Lastly, Metrolinx mentioned that they would share more details about the line this fall. If so, it looks the Preliminary Design Business Case (PDBC) was pushed back to this fall after Metrolinx stated the PDBC would be released late this summer. However Metrolinx also stated that they would share more information about the project in the next few weeks.
View attachment 266286
As a result I asked when the PDBC would come out to figure it out once and for all. I'm fairly anxious to know more info about the line and hopefully we can see it as soon as they can.