Toronto One Crosstown Towers I, II, III, and The Crest | 129.86m | 39s | Aspen Ridge | Core Architects

Are you referring to this?

Update: No movement has been made on this end as of yet upon my visit here earlier today...

20240225_161039.jpg


Either way, my obligatory shot of the ongoing project at hand...

20240225_155859.jpg
 
Taken today, March 29th, 2024

View attachment 552138

Once the western tower tops out in April, more resources will be diverted to the Middle and Eastern buildings. Spring / Summer weather is when they work the quickest so expect these to top out rather quickly.

Western Tower Approximately 30 ish out of 32 = 94% (Occupancy - Jan 2025 - 9 Months to go) - At this pace, should top out some point in April
Middle 18 out of 39 = 46% (Occupancy (March 2025 - 11 months to go) - At this pace, should top out some point in July
Eastern 20 out of 34 stories = 59% (Occupancy (April 2025 - 1 year to go) - Should top out some point in June
 