What the Hell..............Where the communications???..................Does the right hand know what the left is doing???
Taking the other haft to the eye doctor today and waiting for our bus, noticed the #8 bus turning off Central Parkway, not Elm Dr like it normally does that was odd. Head to Heartland to swap data from the old laptop to a new on after the Dr.
Hit CCTT and scratch my head at what I was seeing at the terminal. CCTT was closed to all buses a week ago to allow things to be install across the driveways. All of Rathburn was fully pave where it hadn't been paved as well.
Saw cutting was under way in front of CCTT to install a gas line as I saw the marking on the road last week, Excavation was to start at City Centre and go west to Duke of York for the gas line. Why not do it when there was no paving in place?? Was told they were doing backward.
Got on the #3 bus with no problems until we turn onto Elm and came to a complete stop. The bus and traffic couldn't go east on Elm and cross Hurontario St as it was close and block off. The bus backup to go backup to Burnhamthrope to get to Hurontario to get to Elm. Elm is 100% close on the west side of Hurontario to allow various infrastructure to be install. The bus driver had no info on the road closure and was on the phone to Dispatch about the closure.
Either the closure happen after he pass through the area to get to CCTT or was a relief driver who wasn't told the buses were on detour or how long it would be. No info at CCTT to inform riders that the 3 and 8 were on detour.
Did the contractor not pass on info onto Transit management about the closure or did transit fail to inform everyone of the plan detour??
Then the contractor has add asphalt curbs in front of the existing shelter preventing buses get to the sidewalk once traffic is shift to the south side of Rathburn in July. Are they going to put the wood platforms in front of the curb to allow riders on/off the Buses??