Regarding occupancy, we've been given a revised occupancy date of Oct. 9 (West Tower, office).
What was your original occupancy date?
If they're up to grade that might be a transfer slab they're pouring, which would explain both why it doesn't seem like they've done much lately (there's a lot of work to set up the forms and rebar, with little visible progress), and why it seems like there's so much happening now (it's a large, continuous pour with many trucks lined up and lots of people running around).
They also tend to do transfer slabs on weekends, because of the traffic impacts of all those concrete trucks lining up