*sigh* The King Road project was slid over a Thanksgiving weekend iirc. At the time it was streamed live, with lots of ML publicity. As it happened IIRC one of the sub's was using proprietary technology and had not been warned about the streaming, so it was cut on and off all weekend depending on what could be seen on camera. While CN had a shoofly for freight, there was no VIA or GO service through the site at the time.
The West Toronto slides (there were a couple) also happened over weekend windows with the CP line severed for the duration of the slide.
As to the production quality, you'd have to ask ML if they had a Hollywood quality version. My dusty memory says they did.
- Paul