Active Member
Phase 2 should actually start before the full completion of Phase 1. I believe the critical path to completion more hinges on when they can use the new GO bus terminal and that will open before the tower as a whole does.
View attachment 172382
Phase 2 should actually start before the full completion of Phase 1. I believe the critical path to completion more hinges on when they can use the new GO bus terminal and that will open before the tower as a whole does.
From posting above the GO bus terminal is not expected to open until March 2020 and Phase 2 of the Project will probably be starting by early summer 2020Yes the bus terminal is supposed to be open by the end of this year - so I imagine that it will be under construction within the next 12 months.
The latest @Michael62 update stitched:Not it's not the Hanging Gardens on Babylon Friday
Westside Story: Not much change since yesterday so here's just today's photos
View attachment 172164
View attachment 172165
Some, not quite Corinthian Columns have been delivered to the site. Looking towards the hoarding along Bay St lying on the delivery area you may notice the top portion of what looks like aluminum or galvanized steel columns. They are at least 10m in length and have a square flange welded to the bottom and a sort of nipple at the top. These columns will be holding up the canopy that runs the whole length of the building along Bay St. Maybe someone else can get a better shot of these from a different angle because they are quite impressive. They also come with assorted beams that also look aluminum or galvanized steel. For all, I know they could be zinc or titanium or even lithium to power the lights, nothing about the construction of this building surprises me anymore, I'm just open-mouthed amazed all the time.
View attachment 172166
Eastside Story: (this photo is the same zoom as the first two photos)
View attachment 172168
A closer look shows us a brand new construction office in white with blue supports, just hanging from the east side of the tower office, like the mythical Gardens of Babylon. How that worker, in the hi-vis orange vest, is just hovering there is beyond me, maybe jetpacks. You may also notice that work has begun on the formwork for what will be the floor of level 03.
View attachment 172169
The timeline posted above says March 2020 though...are we sure it'll be open end of 2019?Yes the bus terminal is supposed to be open by the end of this year - so I imagine that it will be under construction within the next 12 months.