Great summary Michael,
We received this today, related to the work schedule.
Dear neighbours,
Below is a brief update on the progress of the CIBC Square project.
81 Bay Street
Work on our
81 Bay Street project continues to progress well. The tower core walls are being formed and poured from level P1 to the underside of the ground floor. The parking garage slabs continue to be formed and poured, with completion of the levels P1, P2 and P3 slabs approximately 25%, 60% and 65% complete, respectively. The ground floor slab elements on the west side of the site are currently scheduled to commence installation in May.
Next week, EllisDon our General Contractor will be continuing to work on the concrete foundation and support wall near Yonge Street. This will require lane closures on Yonge street, preventing access to the
18 Yonge Condominium building from Yonge Street between 10 a.m. and 3 p.m. on April 30th and May 2nd through May 4th. There will be two off-duty Toronto police officers on site during these times directing vehicles and pedestrians to maintain a safe situation.
Also, a Noise Bylaw Exemption permit for delivering reinforcing steel to the job site from 6 a.m. to 7 a.m., Monday through Friday, has been granted to EllisDon by the City of Toronto. The permit is valid for three months. The Board of Directors at both the
18 Yonge Condominium and the Pinnacle Condominium buildings were consulted and agreed as part of the approval process.
Rail corridor
The construction of the foundations supporting the future park over the rail corridor will be completed early next week. We understand this construction phase has involved loud construction activities and we thank you again for your patience.
The next phase of construction will consist of erecting the steel structure to support the park. This activity will begin next week and is expected to last about 10 to 12 months. The steel columns and trusses will once again be installed during the night at night, as we are only authorized to do construction work in the rail corridor when the tracks are taken out of service. EllisDon will be taking various measures to mitigate the impact of this work for our neighbors, including:
• The use of electric equipment for bolting, quieter than pneumatic tools
• More efficient and quieter welding techniques
• Material delivery during the day to reduce the movement of trucks at night
We will continue to share construction updates and work schedules to keep you informed.