BLOOR STREET
Construction Update
January 20, 2009
Bloor Street Transformation Update
Yonge St. to Church St . :
Boulevard works on the south side between Church St. and Park Rd. are close to completion, with the new granite pavers and curb installed. Some planter work and additional adjustments are required before the boulevard is completely opened up. Construction continues on the south side, between Park Rd. and Yonge St .
Construction, between Yonge St. and Park Rd. , on the north side, will begin following the waterproofing of the Hudson ’s Bay Centre basement roof, which extends underground, beyond their building face. The property owners are undertaking this work, on their property. Temporary asphalt has been installed on the City sidewalk to provide a safe, walkable surface during the winter months. Once all work below the boulevard has been completed, the contractor will return to install the granite.
Construction of the north side of Bloor St. East , between Park Rd. and Church St. is scheduled to begin, following completion of the south side.
Yonge Street to Avenue Road:
Powerline Plus (PLP), has returned, to continue working on the rebuilding of Hydro Chambers (aka “Manholesâ€), located predominantly on the north side of the street, in the curb lane. The following is a schedule, by address, provided by the City and Toronto Hydro:
50 Bloor St., at Balmuto St. from Jan. 5 – 30, 2009
110 Bloor St., west of St. Thomas from Jan. 5 – 13, 2009
144 Bloor St. (A), east of Avenue Rd. from Jan. 5 – 23, 2009
144 Bloor St. (B), east of Avenue Rd. from Jan. 19 – Feb. 6, 2009
130 Bloor St., east of Avenue Rd. from Jan. 26 – Feb. 13, 2009
With respect to the Bloor Street Transformation, a preliminary schedule has been produced for Bloor St. West . At this time, construction on the water and storm network, as well as the rebuilding of hydro vaults, between Yonge St. and Avenue Rd., will begin following the schedule outlined above.
The following schedule, which was sent to us by the City’s Project Manager, was produced by the contractor, and should be used as a guideline for reference, only. It is a broad summary of the “projected†boulevard work.
Mid-April to early July, Bay St. to Yonge St., North Side
Mid-May to late August, Bay St. to Avenue Rd., North Side
Early August to mid-October, Bay St. to Yonge St., South Side
Early September to early December Bay St. to Avenue Rd., South Side
Please Note – These construction schedules have been provided to us by the City contractor. Given the extent and complexity of the project, changes to the schedule may occur