2. Two Lane Closures
QEW WB&EB Between Hurontario Street and Erin Mills Parkway
Location:
- QEW Westbound from Hurontario Street to Erin Mills Parkway
- QEW Eastbound from Erin Mills Parkway to Credit River Bridge
Date:
Friday July 14 to Tuesday August 01, 2023
Time:
10:00PM to 8:00AM
Purpose:
Ongoing QEW Credit River Improvement Project
Description:
QEW Westbound
Two lane closure of QEW Westbound from Hurontario Street to Erin Mills Parkway
- SUNDAY
- Lane 1: 11:00PM to 6:00AM
- Lane 2: 11:00PM to 5:00AM
- MONDAY, TUESDAY, WEDNESDAY & THURSDAY
- Lane 1: 11:00PM to 6:00AM
- Lane 2: 11:00PM to 5:00AM
- FRIDAY
- Lane 1: Midnight to 6:00AM
- Lane 2: Midnight to 5:00AM
- SATURDAY
- Lane 1: 11:00PM to 7:00AM
- Lane 2: Midnight to 6:00AM
QEW Eastbound
Two closure of QEW Eastbound from Erin Mills Parkway to the Credit River Bridge
- SUNDAY
- Lane 1: 11:00PM to 5:00AM
- Lane 2: 11:00PM to 5:00AM
- MONDAY, TUESDAY, WEDNESDAY & THURSDAY
- Lane 1: 10:00PM to 5:00AM
- Lane 2: 11:00PM to 5:00AM
- FRIDAY
- Lane 1: 11:00PM to 7:00AM
- Lane 2: Midnight to 6:00AM
- SATURDAY
- Lane 1: 11:00PM to 8:00AM
- Lane 2: Midnight to 7:00AM
Impact:
- Traffic Disruptions are anticipated.
- Overnight Construction activities.
- All closures are weather dependent.
- Closure dates are subject to change and may not take place on all the dates listed above.
3. Nightly Lane and Ramp Closures
QEW Westbound from Hurontario Street to Erin Mills Parkway, Hurontario Street On-ramps and Mississauga Road Off-ramp
--UPDATE--
Location:
- QEW Westbound from Hurontario Street to Erin Mills Parkway
- QEW Westbound On-ramps at Hurontario Street
- QEW Westbound Off-ramp to Hurontario Street
- QEW Westbound Off-ramp to Mississauga Road
Date:
Thursday July 27 to Friday July 28, 2023
Time:
9:00PM to 6:00AM, nights
Purpose:
Ongoing QEW Credit River Improvement Project
Description:
QEW Westbound ClosuresTwo lane closures on QEW Westbound from Hurontario Street to Erin Mills Parkway
- Lane 1: 9:00PM to 6:00AM
- Lane 2: 10:00PM to 6:00AM
QEW Westbound On-ramps at Hurontario Street Full closure of the On-ramps
QEW Westbound Off-ramp to Hurontario StreetFull closure of the Off-ramp
QEW Westbound Off-ramp to Mississauga RoadFull closure of the Off-ramp
Impact:
- Traffic Disruptions are anticipated.
- Overnight Construction activities.
- All closures are weather dependent.
- Closure dates are subject to change and may not take place on all the dates listed above.
4. Ramp Closure - Long Term
QEW Eastbound, Mississauga Road On-ramp
Location:
On-ramp to QEW Eastbound from Mississauga Road
Date:
Monday July 31, 2023, to Saturday September 16, 2024
Time:
Continuous starting Monday July 31, 2023 at 5:00AM to Saturday September 16, 2024 5:00AM
Purpose:
Ongoing QEW Credit River Improvement Project
Description:
Full closure QEW Eastbound On-ramp at Mississauga Road
Detour:
Access to QEW Eastbound will be available via South Sheridan Way Eastbound On-ramp.
Impact:
- Traffic Disruptions are anticipated.
- All closures are weather dependent.
- Closure dates are subject to change and may not take place on all the dates listed above.
5. Ramp Closure - Short Term
QEW Eastbound, Mississauga Road On-ramp
Location:
On-ramp to QEW Eastbound from Mississauga Road
Date:
Friday July 28 to Monday July 31, 2023
Time:
Continuous starting Friday July 28 at 10:00PM to Monday July 31, 5:00AM
Purpose:
Ongoing QEW Credit River Improvement Project
Description:
Full closure QEW Eastbound On-ramp at Mississauga Road
Detour:
QEW Eastbound will be detoured via South Sheridan Way Westbound, Erin Mills Northbound to QEW Eastbound On-ramp at Erin Mills interchange.
Impact:
- Traffic Disruptions are anticipated.
- Overnight Construction activities.
- All closures are weather dependent.
- Closure dates are subject to change and may not take place on all the dates listed above.