TTC rollout schedule is on the Metrolinx website - http://www.metrolinx.com/en/docs/pdf/board_agenda/20110915/Presto_update20110915.pdf
Agreement should be signed in November 2011. Construction from March 2012 to March 2013. Rolled out in subway stations from April 2013 to July 2014. Streetcars from April 2013 to 2015. Buses from summer 2013 to 2015. Substantially complete before the Pan-Am Games. Legacy fare media withdrawn 6 months after roll-out complete. Seems they are looking at Guelph and Grand River as well.
It will take 1.5 to 2 years to have it rolled out in subway stations, when it's already rolled out in some subway stations? Oy vey...