So I was by recently and the pavers look to be onsite, at each stop at least 3 pallets of them. I remembered that I'd seen some lying around but wasn't absolutely sure if I was remembering that correctly. Also, it seemed like the reason they hadn't been laid is that when the new platforms went in the height had changed, or maybe everything had sunk from before so I think they have regrading work to do, I wish they'd get on with it.
I understand where you're coming from, but I don't have a lot of patience with further excuses on this project. This was work that was supposed to be done while KQQR and Roncesvalles North gate construction closed transit access from the south. They had 7 months! If they had stuck to getting it done when scheduled, all of these delays with sourcing materials and site conditions would have been dealt with when no one was trying to use any of these platforms. As far as I'm concerned, the work not being complete is a problem, someone needs to take ownership of it and get it resolved because at this point it seems like everyone is too busy pointing at someone else instead of getting work done.