Well the good news is that it looks track-ready. What might slow it down is 1) the date CN has in mind for cutting it into their mainline and 2) the signalling commissioning date. I would assume that both those events are already scheduled and even if track laying happens tomorrow, those dates would not change. That’s just how the Class 1s operate!A month later, not much (visible) progress, though there was a small crew doing some work east of the Mary Street bridge.
Last update I’ve seen is a ‘late 2024 completion’, anyone know if that’s been updated?
I’m hoping it will be done for the fall schedule release.