Here's another angle from when I took the East Don Trial this morning on the way to The Driveside's South Scarborough Loop ride. Wonder if this work will end up being done by the end of this year?
I just emailed TRCA to ask how the work is progressing, if/when I hear I will, of course, post.As of today, the concrete footing for the bridge ramp is complete, but the ramp is not in place yet. Couple of weeks maybe?
I also did that last week and gave them a nudge last night since they didn't respond.I just emailed TRCA to ask how the work is progressing, if/when I hear I will, of course, post.
The TRCA hasn't posted anything regarding the Phase 3 trail on their website. They seriously need to get their acts together.Now that the completion of Phase 1 is in sight, is there any progress on planning Phase 3 (a trail underneath Eglinton, to connect Phases 1 and 2)?
I also did that last week and gave them a nudge last night since they didn't respond.
The TRCA hasn't posted anything regarding the Phase 3 trail on their website. They seriously need to get their acts together.
To illustrate, below are some (potato quality) captures from the applicant's restoration plans, showing trails through the current golf course.Now that the OLT decision has gone against the City on 155 St. Dennis (assuming no appeals), I expect the design to revert the trail in phase 3 to the golf course side. The design will take awhile to advance.
With Christmas coming, we could also ask for another present --- Phase 4 north of Lawrence, connected to Betty Sutherland. But that will not happen in our lifetime. Another golf course in that space.In fairness to the TRCA, phase 3 was rightly put on hold because as proposed (avoiding the golf course lands and sticking to the east side of the river), it was going to be very environmentally destructive, more expensive, and would not be meet accessibility standards due to steep grades.
***
Now that the OLT decision has gone against the City on 155 St. Dennis (assuming no appeals), I expect the design to revert the trail in phase 3 to the golf course side. The design will take awhile to advance.
With Christmas coming, we could also ask for another present --- Phase 4 north of Lawrence, connected to Betty Sutherland. But that will not happen in our lifetime. Another golf course in that space.
Metric is currently placing the granular base for the remaining 1.2 km of trail, with paving scheduled for next week, weather permitting. The southwest approach structure is also expected to be completed next week.
By mid-November, Metric will begin work on the 80m access route (from the Taylor-Massey Creek Bridge to Charles Sauriol Park). This work will include removals, grading, installation of armourstone walls, paving, decorative bollards, and trail gates.
We anticipate that the majority of the work will be completed before the end of the year, weather permitting. Some restoration activities, terraseeding, and coloured paving will be deferred to early spring.
No word about the big bridge leading off the Taylor Creek Trail?Finally got an update from city staff this morning regarding the remaining East Don Trail Phase 1 works. They expect the TRCA's project website to be updated soon.